home *** CD-ROM | disk | FTP | other *** search
/ Apple Reference & Presen…rary 6 (Reseller Edition) / Apple Ref. & Pres. Lib.v6.0.toast / pc / 5-Fonts & Software / Applications / MacProject II / MacProject II Help / card_37714.txt < prev    next >
Text File  |  1989-09-27  |  2KB  |  51 lines

  1. -- card: 37714 from stack: in
  2. -- bmap block id: 0
  3. -- flags: 0000
  4. -- background id: 3633
  5. -- name: Calendars and Resources
  6.  
  7.  
  8. -- part 36 (button)
  9. -- low flags: 00
  10. -- high flags: A003
  11. -- rect: left=246 top=245 right=266 bottom=445
  12. -- title width / last selected line: 0
  13. -- icon id / first selected line: 0 / 0
  14. -- text alignment: 1
  15. -- font id: 3
  16. -- text size: 10
  17. -- style flags: 0
  18. -- line height: 13
  19. -- part name: Setting Calendars
  20. ----- HyperTalk script -----
  21. on mouseUp
  22.   go card id 90432
  23. end mouseUp
  24.  
  25.  
  26. -- part contents for background part 6
  27. ----- text -----
  28. Calendars define the working times‚Äîhours, days of the week, dates, and year‚Äîfor the project or for a resource.
  29.  
  30. In MacProject II, each project has a primary calendar called the Project Calendar. This calendar initially specifies a standard 5-day work week, with work hours from 9:00 a.m. to 5:00 p.m., and covers the current year plus the following 2 years. You can change any of the settings.
  31.  
  32. A resource is whatever is assigned to work on a task. Most often, it is a person or group of people, but it can also be equipment or
  33.  
  34. -- part contents for background part 7
  35. ----- text -----
  36. materials. If you have resources whose working times differ from the Project Calendar‚Äôs working times, you can establish a special calendar for each one.
  37.  
  38. MacProject II always uses the Project Calendar to calculate task durations, and it uses the Project Calendar for resource durations if the resource has not been assigned another calendar.
  39.  
  40. You ordinarily set your calendars first, assign them to resources as necesary, and then assign resources to tasks.
  41.  
  42.  
  43.  
  44.  
  45. -- part contents for background part 27
  46. ----- text -----
  47. Schedule Information
  48.  
  49. -- part contents for background part 28
  50. ----- text -----
  51. Calendars & Resources